Below is a sample “requirements record,” which outlines theresources, constraints, and other parameters of a project.
Project Title: The Jacksonville Company Management Information System
Project Manager: Michael James
Date: May 14, 2002
Requirement:
A Management Information System (MIS) to support a corporate officeconsisting of fifty people. The MIS will produce forms, reports, data, andanalyses specified by the Information Systems Department’s needs analysis (MISNeeds Analysis, dated January 30, 2002). The MIS will be operational no laterthan April 1, 2003.
Assumptions: The following assumptions have been made in determining theresource requirements for this project:
Jack Smith will be assigned as the technical lead for the project
Jean Jordan and Bill Williams will be available 50% of their time tosupport the project manager with clerical and financial assistance
The IS department will complete their technology assessment by June 1, 2002
This project has priority one status
Constraints:
Given the number of competing projects at Jacksonville, the schedule can bemet only with complete functional area support of resources and materials
A budget of $200,000 may be insufficient to support IS’s technologyrecommendations
Required Resources:
Technical lead
Two full-time programmers
One part-time programmer
Two design engineers
One systems engineer
Functional Groups Participating:
Engineering
Information Systems
Software Development
From “The Project ManagementWorkshop,” © 2001 James Taylor. Allrights reserved.
Published by AMACOMBooks, Division of AmericanManagement Association, 1601 Broadway, New York, NY 10019, To order call:800/262-9699.
Schedule, engage, and pay your staff in one system with Workforce.com.